Groveland Bay Improvements Project Update 10/29: Schedule is weather dependent and subject to change.
McKenzie Point
Week of Oct. 25: Water main and stormwater force main installation.
Week of Nov. 1: Water service replacement and installment. Road subcutting is expected to begin. Access will be limited or eliminated.
Week of Nov. 8: Road subcut to be finished and curb and gutter installation will begin. Access will be limited or eliminated. Driveway access will be lost for McKenzie Point residents to allow curb and gutter to cure.
Week of Nov. 15: Paving base layer of road. This is expected to take 1-2 days and access will be limited.
Beechwood Avenue
Week of Oct. 25: Water service replacement. Storm sewer will begin Friday. Access will be limited.
Week of Nov. 1: Complete storm sewer and begin road subcut.
Week of Nov. 8: Curb and gutter installation. Driveway access will be lost to let the curb and gutter cure.
Week of Nov. 15: Paving base layer of road. This is expected to take 1-2 days and access will be limited.
Groveland School Road, Bay Lane, Bay Circle
Week of Oct. 25: Utility structures raised to final grade.
Week of Nov. 1: Paving final layer of pavement scheduled for Nov. 1st.
Bay Street & Grays Bay Boulevard
Week of Oct. 25: Roadway was subcut.
Week of Nov. 8: Curb and gutter installation scheduled for the 8th. Driveway access will be lost to allow the curb and gutter to cure.
Week of Nov. 15: Paving base layer of road.
Abel Lane
Week of Nov.1: Curb and gutter to be finished at the west end.